COMISION FEDERAL DE ELECTRICIDAD: Unbalance in the National Interconnected System Affected the Electricity Supply to 10.3 Million Users in the Country; Simulation Model will Accurately Indicate Failure

The operation output of two transmission lines between the Lajas and Güémez substations in 400 thousand volts due to oscillations in the National Interconnected System, caused the frequency of the System to increase by 61.8 hertz and 16 power plants went out of operation, 1,714 MW of photovoltaic and 877 MW of wind, for an amount of 9,262 megawatts. Read More »